Exciting progress continues at Enkang Phase 3, where Block B and Block F are rapidly advancing through the final stages of construction. Every milestone achieved brings us closer to delivering modern, high-quality homes in one of Nairobi’s fastest-growing neighborhoods along Ngong Road.
As finishing works accelerate, future homeowners and investors can clearly see the transformation taking place across the development.

INTERIOR FINISHING PROGRESS
Joinery Works
Joinery installation continues at a steady pace across both blocks and has now reached the 10th Floor.
Works include the installation and fitting of:
- Internal doors
- Wooden finishes
- Granite Kitchen Countertops work
This marks another important milestone in preparing the apartments for final interior finishes.



Sanitary Installation
Sanitary installation has officially commenced and is currently underway on the 2nd Floor.
Works include installation of:
- Water supply systems
- Drainage systems
- Bathroom plumbing
- Sanitary fittings
This milestone represents the beginning of Mechanical, Electrical and Plumbing (MEP) finishing works.


EXTERIOR FINISHING PROGRESS
Sanitary Installation
Exterior painting has now commenced on both blocks.
The painting works have made excellent progress and are expected to be fully completed within the next two weeks.
Once complete, the buildings will showcase their final architectural finish and significantly enhance the overall appearance of the development.



INFRASTRUCTURE WORKS
Sewer Connection
Infrastructure works continue with the ongoing sewer connection for both Block B and Block F.
Completion of these essential utility works will prepare the buildings for the final testing and commissioning stages before occupation.

NEXT MILESTONES
The upcoming construction milestones include:
- Completion of external painting
- Continued sanitary installation
- Progression of joinery to upper floors
- Completion of glazing installation
- Completion of sewer infrastructure
- Electrical and mechanical finishing works
- Final inspections and commissioning
CONCLUSION
Enkang Phase 3 continues to make strong progress as Block B and Block F advance through the final stages of construction.
With interior finishes accelerating, exterior painting nearing completion and essential infrastructure works underway, the project remains firmly on course toward successful completion.
The continued progress reflects Enkang’s commitment to delivering quality homes while maintaining construction standards and timelines.