FEBRUARY 2026 PHASE 3 CONSTRUCTION PROGRESS UPDATE

Enkang Phase III development along Ngong Road continues to make strong progress, with construction moving steadily across all three residential blocks. As one of the most promising residential projects in the area, Enkang is delivering modern living spaces while benefiting from major infrastructure developments nearby.

Here is the latest construction progress update for Phase III, including developments in Blocks B, F, and A, as well as key improvements happening around the neighborhood.

OVERVIEW

Phase III of Enkang Residence consists of three residential blocks designed to provide modern and spacious apartment living along Ngong Road.

  • Block B & F began construction in late 2024 and are now in the advanced finishing stages, with completion expected in 2026.
  • Block A, the third and final block, commenced in October 2025 and is progressing steadily toward its expected completion in June 2027.

Construction across the entire phase remains on schedule, with several key structural and finishing milestones already achieved.

BLOCK B & F CONSTRUCTION PROGRESS UPDATE

Blocks B and F are currently in the final stages of exterior and interior finishing works.

EXTERIOR WORKS

Significant progress has been made on the building exterior:

  • External finishing works are ongoing.
  • Balcony railings have been installed in all units from the 1st to the 14th floor, adding both safety and aesthetic appeal to the development.

INTERIOR WORKS

Interior finishing works are also progressing smoothly:

  • Interior skimming has been fully completed.
  • Tiling works have been completed from the 1st to the 14th floor, bringing the apartments closer to the final finishing stage.
  • Internal and external door installations are ongoing, currently reaching the 5th floor.
  • Window frame installations are also underway, currently progressing on the 5th floor.

BASEMENT CONSTRUCTION

Work on the basement continues to move forward with:

  • Concrete pouring currently underway, strengthening the structural foundation of the development.

With these major milestones achieved, Blocks B and F remain firmly on track for completion in 2026.

BLOCK A CONSTRUCTION PROGRESS UPDATE

The third and final block of Phase III, known as Block A, began construction in October 2025 and is progressing as planned.

CURRENT CONSTRUCTION WORKS

  • Basement works have been fully completed, marking a major structural milestone.
  • Structural reinforcement works are ongoing to support the next stages of construction.
  • Preparation works are underway to allow gravel pouring at the first-floor level, which will support the development of the building’s floor slab.

With construction progressing smoothly, Block A is expected to be completed by June 2027.

NEIGHBORHOOD DEVELOPMENTS

One of the biggest advantages of investing or living at Enkang Residence is its location along Ngong Road, an area currently experiencing significant infrastructure upgrades.

These developments are expected to increase property value, improve accessibility, and boost rental demand in the area.

TALANTA STADIUM (OPPOSITE ENKANG)

The Talanta Stadium, located directly opposite Enkang Residence, is nearing completion.

Once completed, the stadium is expected to:

  • Increase commercial activity in the area
  • Drive demand for nearby residential properties
  • Boost long-term property values for developments like Enkang

This landmark project will position the neighborhood as a major urban hub within Nairobi.

NGONG ROAD INFRUSTRUCTURE UPGRADE

In addition to the stadium development, the government is currently constructing a new flyover near Junction Mall along Ngong Road.

This upgrade is expected to:

  • Reduce traffic congestion
  • Improve connectivity between key areas of Nairobi
  • Enhance accessibility to Enkang Residence

Improved road infrastructure is a key driver of real estate growth and investment potential, making Enkang an attractive option for both homeowners and investors.

WHY ENKANG REMAINS A STRONG INVESTMENT

With steady construction progress and major infrastructure developments nearby, Enkang Residence continues to strengthen its position as one of the most attractive residential investments along Ngong Road.

Key advantages include:

  • Prime location along Ngong Road
  • Modern apartment design
  • Strong rental demand potential
  • Nearby infrastructure upgrades
  • Proximity to Talanta Stadium

As construction progresses across all three blocks, Enkang continues to deliver on its promise of quality living and long-term value appreciation.

PROJECT OUTLOOK

The development remains on track across all three blocks, with substantial progress made in both structural and finishing works.

With Blocks B and F nearing completion and Block A advancing steadily, the project continues to move forward according to plan.

Combined with the surrounding infrastructure upgrades, Enkang Residence is positioned to offer strong residential appeal and long-term investment value.

STAY UPDATED

Follow our journey and receive real-time updates on the construction progress and upcoming milestones.

📲 Facebook | Instagram | TikTok — @EnkangKenya

Enkang — We’re where you want to live.

Stay connected.

Leave a Comment

Your email address will not be published. Required fields are marked *